ICCO Completes 76.2 km Section III of Beji–Jangara–Wushishi Road

International Consolidated Contractors Offshore SAL Ltd (ICCO) has completed the Design and Construction of Section III of the Beji–Jangara–Wushishi Road in Niger State. The section runs 76.2 km, from km 0+000 to km 76+200. The Ministry of Works and Infrastructural Development issued the Certificate of Completion on 8 May 2025, reference MOW/CPC/2025-048.


This article sets out who awarded the contract, what it covered, and what the Ministry's certificate says about how the work was done. The rest of this series looks at each part of the road in more detail.

Key facts

  • Project: Design and Construction of Section III of the Beji–Jangara–Wushishi Road, Niger State
  • Contractor: International Consolidated Contractors Offshore SAL Ltd (ICCO), sole contractor
  • Contract No.: MOW/CDB-GB/SIII-22
  • Length: 76.2 km (km 0+000 to km 76+200)
  • Contract price: ₦33,298,345,042 (final value, including variations, unchanged)
  • Duration: 36 months; work began 7 February 2022
  • Certificate of Completion: 8 May 2025, ref. MOW/CPC/2025-048

From award to completion

The Niger State Government awarded the contract to ICCO through a Letter of Award dated 19 January 2022, reference MOW/CONT/2022/14. The contract price was ₦33,298,345,042, with a contract duration of 36 months.

Work began on 7 February 2022. The road was taken over on 6 February 2025, and the Certificate of Completion followed on 8 May 2025.

Date Milestone
19 January 2022 Letter of Award (ref. MOW/CONT/2022/14)
7 February 2022 Work begins (date of commencement)
6 February 2025 Road taken over
8 May 2025 Certificate of Completion issued (ref. MOW/CPC/2025-048)

Full design-and-build scope

The contract covered the design, engineering, procurement and construction of approximately 76.2 km of trunk road. It included all associated civil, structural, drainage, pavement, utility and road-safety works needed to deliver the road to bituminous-pavement standard.

As a design-and-build contract, ICCO was responsible for the road from initial design through to final construction. This single point of responsibility helps keep design and construction aligned.


The principal works

The principal works included earthworks, a cement-treated subbase, asphalt pavement layers, 20,000 m of longitudinal drainage, 100 culverts and 10 bridges. ICCO also installed 55,000 m of HDPE service ducts and a complete set of road-safety installations.

Item Quantity
Trunk road length 76.2 km
Longitudinal drainage 20,000 m
Culverts 100
Bridges (300 m combined length) 10
HDPE service ducts 55,000 m
W-beam guardrail 18,200 m
Traffic signs, including 5 gantries 270

Rated Very Good

ICCO served as sole contractor on the project. The final contract value, including variations, remained ₦33,298,345,042, the same as the original contract price. A 12-month defects notification period applies.

The Ministry stated that the works were executed to its satisfaction. It rated quality, safety, environmental and social performance as Very Good, and confirmed that there are no outstanding claims, disputes or litigation between the parties.

More on the Beji–Jangara–Wushishi Road

This article is part of a five-part series on the project:

Frequently asked questions

Who built Section III of the Beji–Jangara–Wushishi Road?

International Consolidated Contractors Offshore SAL Ltd (ICCO) designed and built it as sole contractor under a design-and-build contract awarded by the Niger State Government.

How long is Section III?

Section III is 76.2 km long, from km 0+000 to km 76+200.

When was the road completed?

The road was taken over on 6 February 2025, and the Ministry of Works and Infrastructural Development issued the Certificate of Completion on 8 May 2025.

What was the contract price?

The contract price was ₦33,298,345,042. The final contract value, including variations, was the same.

This article is based on the Certificate of Completion (ref. MOW/CPC/2025-048) dated 8 May 2025 for Section III (76.2 km) of the Beji–Jangara–Wushishi Road, Niger State, Contract No. MOW/CDB-GB/SIII-22. Images marked ‘Illustrative’ are AI-generated and those marked ‘Representative’ are free stock photos of similar works elsewhere; none show the actual project site.