Building a Bituminous Trunk Road Across 76.2 km of Niger State

The Beji–Jangara–Wushishi Section III contract delivered 76.2 km of trunk road to bituminous-pavement standard. Every quantity below was measured and certified by the Engineer.


Key facts

  • Road length: 76.2 km
  • Site clearance: 105 hectares
  • Cut and excavation: 710,000 m³
  • Fill and embankment: 2,281,130 m³
  • Cement-treated subbase: 184,404 m³ (200 mm)
  • Asphalt wearing course: 50,000 m³ (1,000,000 m², 50 mm)

Clearing the corridor

Work started with site clearance across 105 hectares and topsoil stripping of 149,000 m³. Topsoil is removed because it is too soft and organic to support a road.

Earthworks

Cut and excavation in road cuttings totalled 710,000 m³. Of this, 480,000 m³ of soft material was reused as fill, 180,000 m³ of soft material went to spoil, and 50,000 m³ was rock.

Fill and embankment reached 2,281,130 m³, made up of 2,101,600 m³ of soft material and 179,530 m³ of hard material. Reusing cut material as fill reduces haulage and the need for borrow pits. Improved subgrade, in two layers (ISG 1 and ISG 2), totalled 553,212 m³.

Earthworks activity Executed quantity
Site clearance 105 hectares
Topsoil stripping 149,000 m³
Cut and excavation 710,000 m³
  – soft material reused as fill 480,000 m³
  – soft material to spoil 180,000 m³
  – rock 50,000 m³
Fill and embankment 2,281,130 m³
  – soft material 2,101,600 m³
  – hard material 179,530 m³
Improved subgrade (ISG 1 and ISG 2) 553,212 m³

About two-thirds of the excavated material (480,000 of 710,000 m³) went back into the road as fill.

The pavement layers


Pavement layer Executed quantity
Cement-treated subbase, 200 mm 184,404 m³
Graded crushed stone base, 150 mm 138,303 m³
Prime coat 1,083,820 m²
Dense bitumen macadam (DBM) base course, 75 mm 62,865 m³
Tack coat 838,200 m²
Asphalt concrete wearing course, 50 mm 50,000 m³ (1,000,000 m²)

Why each layer matters

The cement-treated subbase adds strength and stiffness, helping the road resist deformation under heavy trucks. The crushed stone base spreads loads further before they reach the subgrade.

The prime coat seals the base, while the tack coat bonds the asphalt layers together. The DBM base course carries much of the traffic load, and the asphalt concrete wearing course provides a smooth, durable surface for road users.

Together, these layers form a pavement designed to serve as a trunk road for Niger State.

More on the Beji–Jangara–Wushishi Road

This article is part of a five-part series on the project:

Frequently asked questions

How much earth was moved on the road?

Cut and excavation totalled 710,000 m³, and fill and embankment reached 2,281,130 m³. Improved subgrade added 553,212 m³.

How much excavated material was reused?

Of the 710,000 m³ excavated, 480,000 m³ of soft material was reused as fill. Reusing it reduces haulage and the need for borrow pits.

What are the pavement layers?

A 200 mm cement-treated subbase, a 150 mm graded crushed stone base, a prime coat, a 75 mm DBM base course, a tack coat and a 50 mm asphalt concrete wearing course.

Why is topsoil stripped before building a road?

Topsoil is too soft and organic to support a road, so it is removed first. On this project 149,000 m³ was stripped.